Attachment 1992 MOO DA 92-294 r

1992 MOO DA 92-294 r

MEMORANDUM OPINION AND ORDER submitted by CCB, FCC

Memorandum Opinion and Order

1992-03-20

This document pretains to SAT-MOD-19901031-00062 for Modification on a Satellite Space Stations filing.

IBFS_SATMOD1990103100062_1078735

                                           Federal Communications Commission                                              DA 92—294

                                                                                    Commence        Complete
                             Before the                             Satellite       Construction    Construction    Launch

              Federaévgogfm‘i“:fag%‘s‘,‘%g';‘imss"’“                SpotNet—1       August 1989    January 1993     March 1993
                        shington, V.L.                              SpotNet—2       July 1990      July 1993        September 1993
                                                                    SpotNet—3       January 1991    January 1994    ground spare

    In the Matter of                                                The Authorization Order further stipulated that if these
                                                                    deadlines were not met or extended by the Commission
    National Exchange                File Nos. 4/5—DSS—EXT—90       for good cause shown, the authorizations would become,
    Satellite, Inc.                                                 by their own terms, null and void."
                                                                      3. In February 1990, NEXSAT requested,‘ and was
    For Extension of Time to Construct                              subsequently granted," extensions of its milestone commit—
                                                                    ments. In this First Request, NEXSAT asserted that it was
    and Launch Space Stations in the
                                                                    impossible to make commitments regarding construction
    Domestic Fixed—Satellite Service                                of its satellites until the Commission had acted on its
                                                                    request for orbital reassignment. The Bureau specifically
                                                                    rejected these arguments but granted the First Request
            MEMORANDUM OPINION AND ORDER
                                                                    because of NEXSAT‘s possible confusion about imple—
                                                                    mentation of its milestone schedule while its reassignment
Adopted: March 11, 1992;             Released: March 20, 1992
                                                                    request was pending. At that time, the Bureau further
                                                                    ordered NEXSAT to submit "copies of its construction
    By the Chief, Common Carrier Bureau:                            contracts with the spacecraft manufacturer, including any
                                                                    relevant amendments and notices to proceed no later than
                                                                    October 31, 1990 for SpotNet—1 and no. later than March
                       I. INTRODUCTION                              31, 1991 for SpotNet—2."" The Bureau stated that "failure
  1. National Exchange Satellite, Inc. (NEXSAT) requests            to respond within this time frame will subject the au—
extensions of time in which to construct and launch its             thorizations for these satellites to revocation."""
SpotNet satellites.‘ General Instrument Corporation (GIC)             4. On the eve of the expiration of its revised construc—
opposed a number of these requests‘ and NEXSAT re—                  tion commencement date for SpotNet—1, NEXSAT filed
plied.} For the reasons set forth below, NEXSAT‘s re—               another request for an "cxtension of time in which to file
quests are denied.                                                  construction contracts" for its SpotNet satellites."" In this
                                                                    Second Request, NEXSAT states that because of the
                                                                    unique nature of the SpotNet payload, its negotiations
                       II. BACKGROUND                               with potential manufacturers have been far more detailed
    2. In   November     1988, NEXSAT was authorized to             and complex than is common when contracting for more
construct and launch its SpotNet—l and SpotNet—2 sat—               conventional spacecraft. Further, NEXSAT asserts that the
ellites, and to construct a ground—spare, SpotNet—3                 public interest will be served by granting its request be—
NEXSAT subsequently       filed requests for   orbital              cause NEXSAT, as a new entrant to the satellite commu—
reassignment of its SpotNet—l1 and —2 satellites, which were        nications field, will encourage advances in state—of—the—art
granted in January 19905 The Aummorization Order re—                satellite communications and will add diversity to what
quired NEXSAT to implement its satellites in accordance             NEXSAT characterizes as a shrinking field of existing
with the following milestone schedule:                              satellite service providers. Accordingly, it requests that the
                                                                    commencement of construction deadlines for SpotNets—1,
                                                                    —2 and —3 be extended until April 1991, March 1992 and
                                                                    September 1992, respectively.




_ NEXSAT has requested four extensions of its milestone com—        (Authorization Order).
mitments. See paras. 2—6, infra.                                       Assignment of Orbital Locations to Space Stations in the
    GIC has filed several Oppositions to NEXSAT‘s Requests          Domestic Fixed Satellite Service, 5 FCC Red 179 (1990).
(Opposition to Request for Extension of Time (December 14,          SpotNets—1 and —2 were respectively assigned to the 93° W.L. and
1990), Opposition to Request for Extension of Time (March 18,       1279 W.L. orbital locations.
1991) and Motion for Leave to Supplement Opposition (April          8 Authorization Order at para. 8.
15, 1991)) in which GIC urges us to deny NEXSAT‘s extension         ‘ Letter from Counsel, NEXSAT to Chief, Domestic Facilities
requests or, alternatively, to grant NEXSAT‘s requests with the     Division, February 22, 1990 (the First Request). Although
condition that its authorizations be subject to the outcome of      NEXSAT was originally required to commence construction of
the Commission‘s disposition of GIC‘s petition seeking a change     SpotNet—1 in August of 1989, its First Request for an extension
in the Commission‘s orbital spacing policy from 2° to 3°. The       of this deadline was not filed until February 1990.
disposition of NEXSAT‘s requests are made in accordance with        8 Letter from Chief, Domestic Facilities Division to Counsel,
established domestic fixed—satellite policies. The spacing issues   NEXSAT, June 7, 1990 (the June Tth Letter).
raised by GIC have already been considered by the Commission        ° Id. at 4. The commencement deadline for SpotNet—3 was
in another proceeding (RM—7627, RM—7628) and will not be            unchanged.
addressed herein. See FCC 92—1, released January 15, 1992.          9 June 7th Letter, note 8. supra,
    Reply to Opposition (April 5, 1990).                            ‘! Request for Extension of Time. October 31. 1990 (the Sec—
*   National Exchange Satellite, Inc., 3 FCC Red 6992 (1988)        ond Request).


 DA 92—294                               Federal Communications Commission

    5. While Commission action was pending on this Sec—                                  III. DISCUSSION
 ond Request, NEXSAT filed a "redacted" copy of a con—                8. The milestone schedule which is included in every
 tract with TRW, Inc. Space Technology Group (TRW)                  space station authorization issued by the Commission is
 dated February 21, 1991. This contract authorized TRW              designed to assure that licensees are moving forward with
 to complete, by August 1991,‘" an in—depth design study of         the construction and launch of their systems in a timely
 NEXSAT‘s latest technical proposal to launch four single—          manner. Requiring licensees to make and fulfill realistic
_band satellites instead of the two hybrids originally              construction and launch commitments prevents increas—
 planned. "Assuming the success of that study," NEXSAT              ingly scarce orbital locations from being "warehoused" by
 was allowed 21 days thereafter to accept or reject TRW‘s           licensees. Such warehousing could hinder the availability
 proposal." In conjunction with the filing of this contract,        of services to the public at the earliest possible date by
 NEXSAT requested a third extension of its milestone                blocking entry by other entities willing and able to pro—
 schedule (the Third Request). While the exact dates upon           ceed immediately with the construction and launch of
 which NEXSAT therein proposes to meet its milestones               their satellite systems.‘" Efficient management of the orbit
 are not clear, it appears that construction of SpotNet—1           spectrum resource also requires that licensees implement
 would commence on March 1, 1992."" NEXSAT seeks this               their plans in an orderly manner." Accordingly, exten—
 third extension to "facilitate the continued development"          sions of the milestone schedule are granted only when
 of its SpotNet system.                                             delay in implementation is due to circumstances beyond
   6. NEXSAT‘s latest extension request (the Fourth Re—             the control of the licensee.‘®
 quest) was filed on January 6. 1992. The company has
 recently been engaged in discussions with the EDSAT                     A. Second Request
 Institute (EDSAT), which has studied the needs of the                   9. In support of its Second Request, NEXSAT initially
 national educational community for transponder capacity.           notes that it will require additional construction time
 EDSAT concludes that there should be at least one dedi—            "within which to resolve the difficult technological issues"
 cated national satellite network to meet educational needs.        inherent in what it describes as its state—of—the—art satellite
 Toward that end, NEXSAT and EDSAT have initiated a
                                                                    proposal. While NEXSAT would like more time to exam—
 joint feasibility study of the technical and economic mer—         ine and ultimately to determine the best technology to
 its of the potential use of the SpotNet system to meet             pursue, such business concerns are not beyond an ap—
 EDSAT‘s requirements. Accordingly, NEXSAT now re—                  plicant‘s control and thus are not valid bases for an
 quests "an additional 12 to 18 months" within which to
                                                                    extension of time to commence construction of a
 complete this joint feasibility study and to either "(1)
                                                                    satellite."
 begin construction of the first of the SpotNet satellites, or
 (2) if need be, submit an application to the Commission                 10. NEXSAT further alleges that the public interest
 seeking to modify the SpotNet construction permit in               requires a grant of its extension request in order to assure
 order to conform system design to EDSAT requirements
                                                                    that a "meaningful" amount of competition exists in the
 and/or TRW‘s recommendations.""5                                   satellite communications marketplace."" It presents no evi—
                                                                    dence,    however,   that   strict enforcement of milestone
   7. Nexsat has not withdrawn any of its extension re—             schedules impairs the opportunity for new entrants, such
 quests and it is still possible for the company to meet            as NEXSAT, to compete,. or in support of its veiled con—
 certain deadlines proposed in each. We will therefore
                                                                    tention that active competition does not presently exist in
 consider herein the Second, Third and Fourth Requests.             the domestic fixed—satellite service. Indeed, the Commis—
                                                                    sion‘s "open skies" policiecs are designed to encourage
                                                                    participation by all qualified entities in the provision of
                                                                    competitive satellite communications services."" However,


 2   On September 17, 1991, NEXSAT notified the Commission          n.43 and para. 28.
 that the deadline for completion of this design study had been     ‘8    MCI Communications Corporation, supra; see also Hughes
 extended by the parties until October 31, 1991. That study has     Communications Galaxy, Inc. 5 FCC Red 3423, 3424 (extensions
 been completed. See Letter from Counsel, NEXSAT to Sec—            of milestone schedules generally granted only when delay in
 retary, Federal Communications Commission, January 6, 1992.        implementation due to circumstances beyond the control of the
 3 aArticle 17, TRW Contract. NEXSAT does not argue that this       licensee).
 contingent contract is sufficiently binding to satisfy its com—         See, e.g., American Telephone and Telegraph Company,
 mencement of construction commitments. See, e.g., Letter from      supra, at 5591 (economic considerations and business judgments
 Chief, Domestic Facilities Division to Hughes Communications       are not circumstances beyond a licensee‘s control); MCI Com—
 Galaxy, Inc. (June 7, 1990) (non—contingent construction con—      munications Corporation, supra. at 234. See also P&R Temmer,
 tract fulfills construction commencement condition in satellite    743 F.2d 918 (1984) (licensee proposing innovative technology
 license).                                                          bears risk that it will be unable to meet authorization con—
 4 See Exhibit C of the TRW Contract.                               ditions if technology fails to perform as hoped).
 5 Request for Extension of Time, January 6. 1992 (the Fourth       °" in its Second Request. NEXSAT states that "Jalfter a series
 Request) at 2.                                                     of mergers and acquisitions". AT&T, Hughes, GE Americom
 18 MCI Communications Corporation, 2 FCC Red 233.                  and GTE control most of the (C—band and Ku—band orbital
 " Given the rapidly changing technology in the satellite in—       positions.
 dustry and the uncertainty of traffic growth projections over      *! We have, for example. limited to two the number of initial
 time, the Commission does not even consider applications for       orbital assignments available to each licensee. Additional loca—
 either replacement or expansion satellites that are not intended   tions are assigned to existing licensees only upon a showing that
 to be launched promptly. See, e.g., Assignment of Orbital Loca—    in—orbit satellites are essentially filled and that an additional
 tions to Space Stations in the Domestic Fixed—Satellite Service,   orbit location is needed to satisfy firm customer growth require—
 5 FCC Red 179 (1990), at n.44; Licensing Space Stations in the     ments. See Domestic Fixed—Satellite Service — Orbit Deployment
 Domestic Fixed—Satellite Service, 50 Fed. Reg. 36071 (1985), at    Plan, 84 FCC 2d 584, 603 (1981).


                                       Federal Communications Commission                                            DA 92—294


given the limited availability of domestic fixed—satellite C—     Commission‘s desire to encourage the use of economically
and Ku—band orbital locations, mechanisms have been               efficient hybrids whenever possible, the Bureau specifi—
adopted to assure that orbital locations are not held by          cally rejected allegations that the licensee in Hughes was
entities who are not able to proceed promptly with the            attempting to warehouse its C—band location. Because the
implementation of innovative satellite systems. These             implementation dates for the single—band satellites did not
mechanisms, however, do not inhibit new entry. They               coincide, an extension for one "half" of the hybrid was
merely insure the timely availability of proposed services.       necessary. The licensee in Hughes was also required to
NEXSAT itself is a prime example of the continued abil—           commence construction of its satellite immediately upon
ity of new entrants to seek and receive domestic fixed—           grant of its extension request, so there could be no undue
satellite licenses. While market forces may have promoted         delay in implementation.""
acquisitions and mergers resulting in the consolidation of           14. Here, NEXSAT is contemplating the construction of
some space station licensees, such consolidation has not          four satellites in place of its two originally—proposed hy—
been shown to be the result of restrictive Commission             brids. Unlike the situation in Hughes, this change is not
licensing policies, nor to be contrary to the public inter—       technologically dependent on a revision of the milestone
est.                                                              schedules. NEXSAT further does not propose to begin
  11. Both new entry and the innovative service that it           construction immediately. Rather, under the terms of its
may promote are of little public value if the proposed            arrangement with TRW, NEXSAT has not committed
satellite services are not predictably and promptly made          itself to proceed with construction at any specified time or
available. The strict enforcement of milestone schedules,         with any particular technology, and is free to decide to
which will insure this availability, imposes no greater           proceed in a different fashion, or, indeed, not to proceed
burden on new entrants than it does on existing service           with implementation at all.
providers; an applicant‘s plans, and its ability to imple—          15. NEXSAT nonetheless contends that public policy
ment those plans, are expected to he carefully considered         concerns support a grant of its Third Request. It states
prior to the application process. In sum, we have no              that the NEXSAT/TRW developmental efforts should lead
reason to believe that active competition does not cur—           to the introduction of technologies that could significantly
rently exist in, nor do we believe that our decision today        change satellite communications to the benefit of the
will have a chilling effect on continued open entry into,         public, which would enjoy higher quality, less expensive
the domestic fixed—satellite service. On the other hand,          services.         .
public policy concerns regarding spectrum warehousing                16. As NEXSAT correctly points out, "[rlapid tech—
and the prompt availability of proposed satellite services        nological advances...have marked the period since 1974,
support the continued enforcement of our milestone                when the first commercial domsat was orbited.""" Clearly,
deadlines. We accordingly cannot find that the grant of           technological advancement is a desirable goal."" and one
NEXSAT‘s Second        Request    for an    extension of its      that    has   been   encouraged, through   the Commission‘s
milestone commitments is in the public interest.                  "open skies" policies. It is equally clear, however, that the
                                                                  Commission‘s adoption and enforcement of its milestone
  B. Third Request                                                deadlines has not precluded. technological improvements.
  12. In support of its Third        Request for extension,       As discussed at paragraph 10. supra, our procedural
NEXSAT submits that it needs additional time to make a            mechanisms are designed to assure that orbital locations
"choice of conventional technology versus new, but po—            are held only by entities who are willing and able to
tentiall%/ quite beneficial, technology.""*" As discussed         implement their often innovative proposals.
above,"" this decision is wholly within NEXSAT‘s control             17. NEXSAT finally argues that grant of its Third Re—
and does not therefore justify an extension of the com—           quest will not lead to the exclusion of others who would
pany‘s milestone commitments.                                     use these locations. However. the locations assigned to
  13. NEXSAT argues further that the facts in Hughes              both SpotNet—1 and SpotNet—2 allow for 50—state coverage.
Communications Galaxy, Inc. (Hughes), supra, are analo—           Should these locations become available, it is unlikely
gous to its own and thus support its request for extension.       that they will remain unutilized by either new applicants
Contrary to NEXSAT‘s analysis, however, neither the facts         or current licensees seeking orbital reassignment. If they
nor the underlying rationale of Hughes support a grant of         do remain vacant, of course. NEXSAT may reapply for
its request. In Hughes, the licensee had originally been          these locations, or it may resubmit its application for
authorized to construct and launch two single—band sat—           other available locations when it is ready and able to
ellites. The implementation dates for these satellites were       implement its system.
not identical. Accordingly, when the licensee later pro—
posed to construct a hybrid satellite, it requested that the        C. Fourth Request
implementation schedules be synchronized to allow the                18. In support of its Fourth Request, NEXSAT alleges
hybrid to be constructed and launched in accordance with          that the extension sought will allow it to explore the
the original milestones for the Ku—band satellite, not the        merits of attempting to develop a satellite system in con—
C—band satellite. Since the C—band satellite was to have          junction with EDSAT. EDSAT‘s goal of developing a
been completed earlier than the Ku—band satellite, this           comprehensive, predictable and affordable satellite com—
amounted to a request for an extension of time in which           munications system to meet the needs of the national
to construct and launch the C—band payload. Noting the



°* Reply to Opposition, supre.                                    25     Wold Communications, Inc. v. FCC. 735 F.2d 1465, 1468
*3 See para. 9, supra.                                            51984).
*4 Hughes actually had begun construction of its satellite pur—    8 See 47 U.S.C. § 303(g).
suant to a Section 319(d) waiver.


DA 92—294                                Federal Communications Commission

educational community appears to be highly laudable. We
encourage EDSAT‘s continued efforts to assess its needs
and to secure a system that is best suited to meet those
needs. To the extent that NEXSAT, or any other space
segment provider, is ultimately chosen by EDSAT to pro—
vide the desired service, we will make every effort to
accommodate the parties‘ needs at the time a tangible
proposal is before us."" However, under our long—standing
policies, we cannot allow NEXSAT to continue to delay
implementation of its satellite system based upon specula—
tion that it may be selected to implement the EDSAT
network. NEXSAT originally committed to commence
construction of its first satellite nearly two and one—half
years ago. Now it seeks an 18—month further delay in the
commencement of construction, while giving no assur—
ance that it will ever construct its authorized system. As
discussed at paragraphs 8 and 9, supra, such commercial
and technical considerations are wholly within the control
of the applicant and thus do not support a further exten—
sion of NEXSAT‘s milestone commitments.


                      IV. CONCLUSION
  19. NEXSAT has not shown that either precedent or
policy supports a grant of its extension requests. On the
other hand, there are compelling reasons to deny these
requests. If the broadly stated desires to provide state—
of—the—art technological services, or to examine potential
commercial applications of a system, were sufficient to
support an extension of milestone schedules, any appli—
cant could successfully argue that its deadlines should be
delayed. Thus, there would no longer be any meaningful
assurances that satellite systems would ever be imple—
mented. This is precisely the type of situation that we
intend to proscribe. Accordingly, we cannot find that the
public convenience and necessity will be furthered by the
grant of NEXSAT‘s Requests.


                V. ORDERING CLAUSES
  20. Accordingly, IT IS ORDERED that the requests of
National Exchange Satellite, Inc. for an extension of time
in which to construct and launch space stations in the
domestic fixed—satellite service ARE DENIED.
   21. IT IS FURTHER ORDERED, pursuant to Section
0.291 of the Commission‘s rules on delegations of author—
ity, that the authorizations granted to National Exchange
Satellite, Inc. in National Exchange Satellite, Inc., 3 FCC
Red 6992 for the SpotNet—1, SpotNet—2 and SpotNet—3
satellites ARE DECLARED NULL AND VOID.

  FEDERAL COMMUNICATIONS COMMISSION




  Richard M. Firestone
  Chief, Common Carrier Bureau




27 As discussed at para. 17, supra, NEXSAT is free to reapply        as it is ready and able to implement its system.
for these same, or other available, orbital locations at such time



Document Created: 2015-03-09 17:30:12
Document Modified: 2015-03-09 17:30:12

© 2025 FCC.report
This site is not affiliated with or endorsed by the FCC