                 NARRATIVE STATEMENT: EARTH STATION LICENSE APPLICATION

        By this application, WorldVu Satellites Limited (“OneWeb”), seeks authority to operate
thirteen technically identical CPI 3.5 meter antennas in Clewiston, FL (the “Clewiston Earth
Station”). The Clewiston Earth Station will provide gateway connectivity to OneWeb’s low
earth orbit (“LEO”), non-geostationary (“NGSO”), fixed-satellite service (“FSS”) system, which
was granted U.S. market access in June 2017.1

        The Clewiston Earth Station will allow OneWeb to expand its coverage and service in the
United States. Additional gateway facilities are a critical part of OneWeb’s network
infrastructure as it prepares to begin commercial service.2 Grant of this application will serve the
public interest by facilitating OneWeb’s ability to deliver ubiquitous, state-of-the-art broadband
access to previously unserved and underserved populations in the United States.

I.         Communications with Non-U.S.-Licensed Space Stations

        OneWeb hereby incorporates by reference the OneWeb U.S. Market Access Grant to
demonstrate compliance with the requirements of Section 25.137 of the Commission’s rules for
earth station applicants proposing to communicate with non-U.S.-licensed space stations.3

II.        Spectrum Use and Sharing

       The Clewiston Earth Station will be mounted on fixed platforms. Although the angle at
which the antennas point will change with the tracking of OneWeb’s in-orbit satellites, each
platform will remain stationary. The Clewiston Earth Station will communicate with OneWeb’s
system in the following frequency bands:

          17.8-18.6 GHz (downlink)                      27.5-29.1 GHz (uplink)
          18.8-19.3 GHz (downlink)                      29.5-30.0 GHz (uplink)




1
  See WorldVu Satellites Limited, Petition for a Declaratory Ruling Granting Access to the U.S.
Market for the OneWeb NGSO FSS System, Order and Declaratory Ruling, 32 FCC Rcd 5366
(2017) (“OneWeb U.S. Market Access Grant”) (granting OneWeb market access for its LEO
NGSO FSS satellite constellation).
2
  OneWeb’s first application for a gateway earth station (located in Talkeetna, AK) was filed
with the Commission on June 4, 2018 and remains pending. See IBFS File No. SES-LIC-
20180604-01082. OneWeb anticipates filing a license application for the proposed Southbury,
CT gateway earth station contemporaneously with the instant application.
3
     See 47 C.F.R. § 25.137.


                                                 1


       As illustrated below, OneWeb’s Clewiston Earth Station will operate in a manner
consistent with the Commission’s rules.

        A.     Uplink

               1.       27.5-29.1 GHz

       The Upper Microwave Flexible Use Service (“UMFUS”) has a primary designation in the
27.5-28.35 GHz band in the Commission’s Ka-band Plan, with a secondary designation for
FSS.4 FSS earth stations are permitted in the 27.5-28.35 GHz band and are not required to
provide interference protection to future UMFUS operators if certain conditions are met.5

       The Commission clarified in the NGSO Order that “NGSO FSS systems must operate on
an unprotected, non-interference basis with respect to GSO FSS networks” in the 27.5-28.35
GHz band.6

       FSS is primary in the 28.35-28.6 GHz band, and the Ka-band Plan designated NGSO
FSS as secondary to GSO FSS in this band.7

       In the 28.6-29.1 GHz band, NGSO FSS is primary in the U.S. Table of Frequency
Allocations and has a primary designation in the Commission’s Ka-band Plan.8

        Terrestrial Coordination. Section 25.136(a)(4) of the Commission’s rules allows earth
station licensees in the 27.5-28.35 GHz band to operate in accordance with the terms of their
authorization without providing additional interference protection to UMFUS stations when four


4
  Update to Parts 2 and 25 Concerning Non-Geostationary, Fixed-Satellite Service Systems and
Related Matters, Report and Order and Further Notice of Proposed Rulemaking, 32 FCC Rcd
7809, App. B (2017) (“NGSO Order”); see also 47 C.F.R. § 25.136(a) (“FSS is secondary to the
Upper Microwave Flexible Use Service in the 27.5-28.35 GHz band.”). The Commission’s
current Ka-band Plan is set forth in Appendix B to the NGSO Order (“Ka-band Plan”).
5
  See 47 C.F.R § 25.136(a); see also Use of Spectrum Bands Above 24 GHz For Mobile Radio
Services, Report and Order and Further Notice of Proposed Rulemaking, 31 FCC Rcd 8014,
8036 ¶ 54 (2016).
6
    NGSO Order, 32 FCC Rcd at 7817, ¶ 23.
7
    See Ka-band Plan.
8
  47 C.F.R. § 2.106, NG165; see also Ka-band Plan. Additionally, in the OneWeb U.S. Market
Access Grant, the Commission authorized OneWeb’s uplink operations in this band. OneWeb
U.S. Market Access Grant, 32 FCC Rcd at 5366, ¶ 1.


                                              2


conditions are met.9 Appendix A to this Narrative Statement demonstrates that the Clewiston
Earth Station will satisfy all four conditions.

        The Comsearch Coordination Report attached separately as Exhibit B10 to this application
demonstrates that in the 27.5-28.35 GHz band: (1) OneWeb can operate the Clewiston Earth
Station without causing harmful interference to existing terrestrial deployments, and (2) OneWeb
coordinated with existing licensees in compliance with the Commission’s rules.

       GSO Coordination. OneWeb makes no claim of interference protection from U.S.-
licensed GSO FSS systems in the 27.5-28.6 GHz band. The ITU developed uplink equivalent
power flux density (“EPFDup”) limits to protect co-frequency GSO FSS operations from
unacceptable interference from NGSO FSS systems operating in the same frequencies.
Specifically, in accordance with Article 22 of the ITU Radio Regulations, if the applicable
EPFDup limits are met, then the Commission will consider the NGSO FSS satellite system to
have met its obligations of protecting GSO FSS networks from unacceptable interference.11
OneWeb has demonstrated that it meets the applicable ITU EPFDup limits in all frequency ranges
where these limits apply and certifies that its operations will be compliant with Article 22 and




9
  See 47 C.F.R. § 25.136(a)(4); see also Use of Spectrum Bands Above 24 GHz for Mobile Radio
Services, Second Report and Order, Second Further Notice of Proposed Rulemaking, Order on
Reconsideration, and Memorandum Opinion and Order, 32 FCC Rcd 10988, 11080, Appendix A
(2017) (“Second Spectrum Frontiers Order”) (adopting changes to this rule section). Because
these rule changes are not yet in effect, OneWeb requests the Commission evaluate this
application under the updated Section 25.136(a)(4). Appendix A to this Narrative Statement
demonstrates compliance with this updated rule. In the alternative, OneWeb respectfully
requests a waiver of the current version of Section 25.136(a)(4) of the Commission’s rules to
allow this application to be processed under the updated provision, as set forth in Appendix B to
this Narrative Statement.
10
   The emission designators provided in the Comsearch Reports in Exhibit B reflect the carrier
noise bandwidth (3 dB bandwidth), which is smaller than the necessary bandwidth (typically 15
dB bandwidth), that has been used for this earth station application and for the OneWeb U.S.
Market Access Grant. The difference in bandwidth is less than ten percent. Therefore, this
variance has no impact on the data culling function performed by Comsearch and provides a
more accurate portrayal of the interference potential of OneWeb’s earth station emissions since
the power-spectral density and the receiver noise bandwidth are computed based on the actual
noise bandwidth instead of the necessary or occupied bandwidth.
11
   See NGSO Order, 32 FCC Rcd at 7820, ¶ 32 (“Any NGSO FSS system operating in
compliance with these limits is considered as having fulfilled its obligation under Article 22 of
the ITU Radio Regulations not to cause unacceptable interference to any GSO network.”).


                                                 3


Resolution 76 of the ITU’s rules.12 Consequently, the transmissions from the Clewiston Earth
Station will sufficiently protect GSO FSS systems.

                2.     29.5-30.0 GHz

        The 29.5-30.0 GHz band is allocated to the FSS on a co-primary basis with the Mobile
Satellite Service (“MSS”), with NGSO FSS having a secondary designation to GSO FSS in the
Ka-band Plan.13

         OneWeb makes no claim of interference protection from U.S.-licensed GSO FSS systems
in this band,14 and the transmissions from the Clewiston Earth Station will sufficiently protect
GSO FSS systems because the OneWeb system meets the applicable ITU EPFDup limits in all
frequency ranges where these limits apply.15

         B.     Downlink

       Federal Coordination. Space-to-Earth operations in the bands between 17.7-20.2 GHz
must complete coordination with U.S. Federal systems in accordance with footnote US334 to the
United States Table of Frequency Allocations, 47 C.F.R. § 2.106, prior to being used. Footnote
US334 lists several locations where federal space and earth station operations are primary.
However, the Clewiston Earth Station is located outside the areas of concern in US334.
Therefore, US334 is not applicable to the instant application.

                1.     17.8-18.3 GHz

        In the NGSO Order, the Commission allocated the 17.8-18.3 GHz band on a primary
basis to the terrestrial fixed service (“FS”) and on a secondary basis for FSS, subject to
international power flux-density (“PFD”) limits.16 OneWeb previously demonstrated that

12
  See WorldVu Satellites Limited, Petition for a Declaratory Ruling Granting Access to the U.S.
Market for the OneWeb NGSO FSS System, IBFS File No. SAT-LOI-20160428-00041,
Technical Narrative (“Market Access Application Technical Narrative”) at 33-34; A2-9 – A2-12.
13
     47 C.F.R. § 2.106; see also Ka-band Plan.
14
   See OneWeb U.S. Market Access Grant, 32 FCC Rcd at 5377, ¶ 23(j). Similarly, OneWeb will
operate in this band without seeking protection or causing harmful interference to any co-
frequency MSS operations.
15
  Market Access Application Technical Narrative at 33-34; A2-1 – A2-6. OneWeb believes that
the EPFDup limits associated with the protection of GSO FSS networks would also adequately
protect any GSO MSS network.
16
     NGSO Order, 32 FCC Rcd at 7812, ¶¶ 7-8.


                                                 4


secondary use of this band for its downlink operations will not cause harmful interference to FS
operations because OneWeb’s system meets the ITU PFD limits.17 Consequently, the
Commission authorized OneWeb’s space stations to transmit in this band despite being on a non-
conforming basis at the time.18 Moreover, the Comsearch Interference Analysis Report attached
as Exhibit B19 to this application indicates that there will be no restrictions on OneWeb’s
operations due to interference considerations in this band.

                 2.       18.3-18.6 GHz

        The 18.3-18.6 GHz band is allocated on a primary basis to the FSS, as the NGSO Order
amended the Ka-band Plan to “allow NGSO FSS systems to operate on an unprotected, non-
interference basis with respect to GSO FSS networks in the 18.3-18.6 GHz . . . band[], subject to
international equivalent power flux-density (“EPFD”) limits.”20 The ITU developed downlink
EPFD (“EPFDdown”) limits to protect GSO FSS networks from unacceptable interference from
NGSO FSS systems operating in the same frequencies. Like the EPFDup limits, if the NGSO
FSS system meets the applicable EPFDdown limits, then the Commission will consider the NGSO
FSS satellite system to have met its obligations to protect GSO FSS networks from unacceptable
interference. OneWeb provided calculations for transmissions in this band showing that the
OneWeb system meets the applicable ITU EPFDdown limits in all frequency ranges where these
limits apply.21 The Commission authorized OneWeb’s NGSO FSS system to transmit in this
band.22

                 3.       18.8-19.3 GHz

        The 18.8-19.3 GHz band is allocated to the FSS on a primary basis, and the Commission
recently preserved the primary designation for NGSO FSS systems in the Ka-band Plan.23 The
Commission authorized OneWeb’s NGSO FSS system to transmit in this band.24

17
     See Market Access Application Technical Narrative at 23-26; see also id.
18
  See OneWeb U.S. Market Access Grant, 32 FCC Rcd at 5373, ¶ 16, 23. At the time of this
grant, the Commission had not adopted a secondary allocation for FSS.
19
     See supra note 10.
20
     NGSO Order, 32 FCC Rcd at 7813, ¶¶ 9-10 (citing Section III.D.1).
21
     See Market Access Application Technical Narrative at 33-34; A2-1 – A2-8.
22
     OneWeb U.S. Market Access Grant, 32 FCC Rcd at 5366, ¶¶ 16, 23.
23
     NGSO Order, 32 FCC Rcd at 7814, ¶ 14.
24
     OneWeb U.S. Market Access Grant, 32 FCC Rcd at 5366, ¶ 1.


                                                  5


III.   Waivers

       Appendix B to this Narrative Statement requests any necessary waivers of the current
Section 25.136(a)(4) rule.

IV.    Antenna Patterns

       Appendix C certifies that the Clewiston Earth Station antenna patterns are in compliance
with the relevant sections of Section 25.209.

V.     Radiation Hazard Report

       Appendix D provides the radiation hazard analysis for the Clewiston Earth Station.

VI.    FAA Notification

       FAA notification is not required as the Clewiston Earth Station will not exceed 6.1
meters above ground.

VII.   Conclusion

        As explained above, grant of OneWeb’s Clewiston Earth Station application is in the
public interest and meets the requirements of the Commission’s rules.


                                                   Respectfully submitted,

                                                   WORLDVU SATELLITES LIMITED
                                                    /s/ Mariah Shuman
                                                   Mariah Shuman
                                                   Senior Director, Regulatory Affairs
                                                   1785 Greensboro Station Place
                                                   Tower 3, Floor 8
                                                   McLean, VA 22102
                                                   1 (703) 731-0691
                                                   mariah@oneweb.net




                                               6


                   APPENDIX A: 47 CFR § 25.136(a)(4) – UMFUS COMPLIANCE

        The Commission’s rules define four elements that, if met, permit an earth station licensee
to operate in accordance with the terms of its authorization without providing additional
interference protection to UMFUS stations in the 27.5-28.35 GHz band.25 Based on the
following analysis, the Commission should authorize the OneWeb Clewiston Earth Station
without requiring additional protection for future UMFUS licensees in Hendry County, Florida.

      1. § 25.136(a)(4)(i)

       The Clewiston Earth Station complies with this section of the Commission’s rules
because there are no other earth stations in the 27.5-28.35 GHz band in Hendry County, Florida.

      2. § 25.136(a)(4)(ii)

        Section 25.135(a)(4)(ii) provides that, in a UMFUS license area with a population
between 6,000 and 450,000 people, no more than 450 people may be within an earth station’s
PFD contour that is equal to or exceeds -77.6 dBm/m2/MHz to avoid having to provide
interference protection to future UMFUS operators. The area around the Clewiston Earth Station
falling within this PFD contour26 is fully contained within Hendry County which has a
population of just over 40,000 people.27 As demonstrated below, the Clewiston Earth Station’s
PFD contour contains far fewer than 450 people.

       Using the ITU RR Appendix 7 Time-Variant Gain (TVG) method, each of the 13
antennas of the Clewiston Earth Station would track a different OneWeb satellite above a
minimum elevation angle of 10 degrees.28 A composite (13 antennas) PFD contour was

25
     See 47 C.F.R. § 25.136(a)(4).
26
  The PFD contour of the Clewiston Earth Station was first computed using existing terrain
features, including earth berms or mounds that exist east and north of the site. As explained in
Section 3 below, these would not be sufficient to comply with the PFD limit in
Section 25.136(a)(4)(iii). To comply with the PFD limit set forth in Section 25.136(a)(4)(iii), an
additional earth berm will be built at the site and the results described herein assume this
additional feature will be present.
27
  See QuickFacts Hendry County, Florida, United States Census Bureau (last viewed June 25,
2018), https://www.census.gov/quickfacts/fact/table/hendrycountyflorida,fl/PST045217.
28
  In this analysis, the population data for each census block within the Clewiston Earth Station
PFD contour comes from the 2010 U.S. Census data. The propagation model implements a 1-arc
second resolution SRTM Digital Terrain Elevation Data (DTED) profile based on the ITU-R
Recommendation P.452-15.


                                                7


developed via proprietary software and compared with the Visualyse PRO software to ensure
consistency. This composite assessed the cumulative distribution function (CDF or joint
probability) of potential interference representing the EIRP towards the horizon and the
propagation statistics by performing the convolution of the individual CDFs. As a result, the
TVG method calculates the area where the PFD limit could be exceeded, assuming a PFD value
that is not exceeded for 99% of the time. The following contains the Clewiston Earth Station
parameters29 and the resulting PFD contour of the analysis:30

                             Clewiston Earth Station Parameters
             ES latitude (NAD 83)                 26° 44' 51.8" N°
             ES longitude (NAD 83)                81° 2' 57.2" W°
             Ground Elevation (AMSL)              5.49 m
             ES antenna size                      3.5 m
             ES input power spectral density      -19.0 dBW/MHz
             ES antenna pattern                   FCC (§25.209(a)(1))
             ES minimum elevation angle           10°
             Number of antennas at site           13




29
   It should be noted that the earth station input power spectral density is 3.4 dB lower than the
maximum provided in the application since the latter includes maximum uplink power control
for rain events exceeding 6 dB. The clear sky value is the most appropriate calculation for this
analysis because uplink power control is not used for fade levels less than 6 dB.
30
  The Clewiston Earth Station’s PFD contour is displayed using Google Maps and then
superimposed on a U.S. Census map to estimate the population within the contour—note that the
population counts for each census block are in parentheses. These images are larger on the next
page.


                                                 8


9


       The next table displays the calculated population for each census block that is within the
Clewiston Earth Station PFD contour:

                                              Assumed Population of Contour Coverage
                         Proportion
     Block                                                      Include        100% of
              Population Covered           Only Completely
      ID                                                        Partially     Pop. in all
                         (estimated)       Covered Blocks
                                                            Covered Blocks      Blocks
     2006           0         15%                 0                 0              0
     2018          17         20%                 0                 4             17
             Total Population                     0                 4             17

The summation of the population in the Clewiston Earth Station PFD contour is approximately:
     0 people (looking at only the populations of those census blocks that are wholly
        contained within the contour and assuming that the populations of the partially covered
        blocks fall outside the PFD contour) or
     4 people (assuming a very conservative proportion of the population in Block 2018 with
        partial contour coverage, based on the estimated geographical area of this Block that falls
        within the PFD contour over its total area).
The third column in the above table would likely never occur because the interference contour
only covers a small portion of Block 2018.
        To verify the population-count in this study and underscore the conservativeness of the
estimated 4-population value, the interference contour was superimposed on a population
distribution grid,31 as depicted in the following figure:




31
    See Gridded Population of the World, NASA Socioeconomic Data and Applications Center
available at http://sedac.ciesin.columbia.edu/data/collection/gpw-v4/maps/services. Note that
due to the low population density in the area surrounding this planned earth station, no data point
in the graph even has a population of 1 person.


                                                10


The estimated population within the contour is 1 person. Consequently, the conservative
estimate of 4 people illustrates that the total population covered by the Clewiston Earth Station’s
PFD Contour is much less than the 450-person limit as set out by this subsection.

     3. § 25.136(a)(4)(iii)

         Based on a search in Google Maps, there are no major event venues, urban mass transit
routes, passenger railroads or cruise ship ports within the Clewiston Earth Station’s PFD contour.
The PFD contour was calculated based on the existing terrain profile (illustrated in red in the
figures below) showing overlap with portions of Highway 27—which is identified as an Other
Principal Arterial by The Federal Highway Administration Office of Planning, Environment, and
Realty Executive Geographic Information System map.32 Nevertheless, UMFUS deployments
will not be impacted by the Clewiston Earth Station because OneWeb will build a berm
(illustrated in blue in the figure below on the next page) resulting in a PFD contour (illustrated in
green in the figures below) that will not overlap with any portion of Highway 27, thus complying
with the requirements of this subsection.




        OneWeb plans to build a 2-meter high earth berm around the location of the proposed
earth station antennas (roughly centered as depicted by the push pin on the above figures). The
berm would follow the curvature of the access road (east to north of the antenna farm) and along
its western border. The proposed berm is shown in blue in the figure below. Should the
Commission approve this application, the berm will be constructed and its impact in terms of
signal attenuation will be measured at the site before commencing transmissions.


32
 See National Highway System Map, U.S. Department of Transportation, Federal Highway
Administration (last visited Mar. 2, 2018), https://hepgis.fhwa.dot.gov/fhwagis/.


                                                 11


          Therefore, the Clewiston Earth Station complies with the requirements of this subsection.

      4. § 25.136(a)(4)(iv)

      The Comsearch Coordination Report in Exhibit B33 demonstrates that OneWeb
completed coordination in compliance with the Commission’s rules.




33
     See supra note 10.


                                                 12


                     Appendix B: 47 CFR § 25.136(a)(4) – Waiver Request

       OneWeb requests that the Commission consider this application under the newly adopted
Section 25.136(a)(4) as OneWeb fully complies with the updated rule as illustrated in Appendix
A. In the alternative, since the rule changes are not in effect as of the submission of this
application, OneWeb requests any necessary waivers of the current Section 25.136(a)(4) rules.

        Grant of this waiver request is consistent with Commission precedent.34 First, in the
Second Spectrum Frontiers Order, the Commission altered the population limits for earth station
coverage specified under Section 25.136(a)(4)(ii) to give satellite operators additional
deployment flexibility.35 Second, requiring OneWeb to comply with the current Section
25.136(a)(4) would become unnecessary as soon as the newly adopted Section 25.136(a)(4)
comes into effect. Third, grant of this waiver is in the public interest because it will facilitate
OneWeb’s ability to build-out the ground infrastructure providing critical support to its LEO
constellation in a timely manner. OneWeb notes the Commission recently granted an earth
station application that contained a similar waiver request.36 For these reasons, OneWeb
respectfully submits that this waiver request is in the public interest.




34
   PanAmSat Licensee Corp., 17 FCC Rcd 10483, 10492 (Sat. Div. 2002) (finding that a waiver
is appropriate so long as the requested relief “would not undermine the policy objective of the
rule in question and would otherwise serve the public interest”).
35
     See Second Spectrum Frontiers Order, 32 FCC Rcd at 11029-32, ¶¶ 124-133.
36
   See O3b Limited, IBFS File No. SES-LIC-20180122-00053, Call Sign E180005 (granted Mar.
8, 2018).

                                                13


               Appendix C: 47 CFR § 25.132 – Antenna Patterns Certification

I, Marc Dupuis, Senior Director of Spectrum Affairs for OneWeb, hereby certify that I

      reviewed the results of a series of radiation pattern tests for the CPI 3.5 meter antenna
       performed by the antenna manufacturer on representative equipment in representative
       configurations, and

      found the test results demonstrate that the CPI 3.5 meter antenna meets relevant off-axis
       gain standards in Section 25.209 of the Commission’s rules, measured in accordance with
       Section 25.132(b)(1).

This certification is dated July 27, 2018 and signed by:


                                                      /s/     Marc Dupuis

                                                     Marc Dupuis
                                                     Senior Director, Spectrum Affairs
                                                     OneWeb
                                                     1785 Greensboro Station Place
                                                     Tower 3, Floor 8
                                                     McLean, VA 22102




                                                14


                                   APPENDIX D: RADIATION HAZARD REPORT

        In accordance with OET Bulletin 65, this Radiation Hazard Report measured radiation
exposure levels in seven zones for two cases—general population and occupational. The
radiation levels calculated for each zone in Section II are derived from the calculations made in
Section I. The results in Section III for OneWeb’s 3.5 meter CPI antenna illustrate any radiation
hazard that may exist for the general public and/or occupationally will be mitigated by limited
access and various protocols to ensure safe exposure levels.

I.         Defined Variables for OET Bulletin 65 Calculated Variables

                                                 OET 65 Calculated
       Variables          Value         Unit                              Formula       Value         Unit
                                                    Variables
                 D=
                                                                  λ=
            Aperture         3.5    Meters                                       c/F       0.0104   Meters
                                                           Wavelength
           Diameter
                  d=                                               PI =
         Subreflector      0.406    Meters         Total Antenna Input           P*p         114    Watts
           Diameter                                             Power
                  η=
                                                                   A=
            Aperture        57%     Percentage                               π(D/2)2      9.62113   Meters2
                                                      Area of reflector
           Efficiency
                                                                    a=
     FCC Designation         Ka     Band                        area of       π(d/2)2     0.12946   Meters2
                                                          sub-reflector
                   F=                                              G=          G=
                           28750    MHz                                                 630965.68   Linear
            Frequency                                    Antenna Gain       4πηA/λ2
                   P=
           Transmitter     114.1    Watts            Antenna Gain dB      10log10(G)        58.00   dBi
          Power Watts
                   p=
                                                                Rnf =
            Number of         1     #                                     Rnf = D2/4λ      293.69   Meters
                                                    Near-Field Region
          Transmitters
                 Rua =
      Closest Point to
                             25     Meters                                                 293.69   >Meters
         Uncontrolled
                  Area                               Transition Region      >Rnf <Rff
                 Rua =
      Elevation angle        10     Degrees                                                704.86   <Meters
       at closest point
                                                                                           704.86   Meters
                                                                  Rff =         Rff =
                                                                                                    Meters
                                                      Far-Field Region       0.6D2/λ         124
                                                                                                    AGL




                                                        15


II.      Radiation Levels in Each Zone

                                                                      Exposure Limits Met
                                                                    General
 Radiation Analysis Zone        Formula       Level        Value                  Occupational
                                                                    Public
                                                                   <1mW/cm2        <5mW/cm2
                                                       mW/cm
 1       Power Sub-reflector         4PI/a    352.48   2               No               No
                                                       mW/cm
 2           Antenna Surface         4PI/A      4.74   2               No              Yes
                                                       mW/cm
 3     Main Reflector Ground          PI/A      1.19   2               No              Yes
                      Snf =
                                                       mW/cm
 4               Near-Field       4η(PI/A)      2.69   2               No              Yes
              Power Density
                 Transition                            mW/cm
 5                              Snf*Rnf/Rnf     2.69   2               No              Yes
          Max Power Density
                  Far-Field                            mW/cm
 6                              PI*G/4πR2       1.15   2               No              Yes
          Max Power Density
                                                       mW/cm
 7        Off-axis Near Field    Snf-20dB       0.03   2               Yes             Yes


III.     Results

        General Public Analysis. OneWeb’s 3.5 meter CPI antennas will be located in an area
clearly marked with Radiation Hazard signage with no access by the general public. Zones 1
through 5 create no concern for the general public as they lie behind this signage where only
authorized personnel may enter. Likewise, Zone 6—Far Field—also creates no concern for the
general public because it develops 124 meters above ground level at a minimum elevation angle
of ten degrees where the general public cannot access. Accordingly, there is no risk of radiation
exposure beyond the acceptable limits.

         Occupational Analysis. Only around the Power Sub-reflector are any radiation levels
exceeded. This measurement is taken at a point between the feed and the sub-reflector. Power
to the transmitters will be turned off remotely whenever work needs to be performed in this
Zone. Signage will mark the area for Radiation Hazard and access by qualified personnel only,
facilitating awareness and safety. Consequently, there is no risk of radiation exposure beyond
the acceptable limits.